Upgrade of the safety PLC Hima from Alquilation plant. Configuration, programming, FAT testes, commissioning and start-up of the SIL3 safety ...
Upgrade of the safety PLC Hima from Alquilation plant. Configuration, programming, FAT testes, commissioning and start-up of the SIL3 safety ...
Supply, installation and configuration of all control systems for the new GPL tank farm from PPS in Aveiro, namely:
...
Study, design and detail engineering of 2 polymer extruders to change from a manual control start-up, in to a full ...
Commissioning and start-up of a Siemens S7 PLC system for the control of the Sulphur Pastillation plant in Petrogal refinery ...
Study and project of the base control engineering system, for the new co-generation plant for Petrogal in Matosinhos, composed of ...
Configuration, test and start-up of one Modbus network for the Schneider Premium PLC , for the control of 20 Rotork ...
Update modification and test of a safety SIL3 PLC HiQuad from Hima, in the Linde Sogás factory in Azambuja, for ...
Configuration, programming, cabinet wiring, test and start-up of one Schneider Premium PLC for the control of the LBC Tanquipor, Tank ...